Ambatovy eBooks - page 60

Summary
Conformity Table of EA with the Terms of Reference (Continued)
ONE Terms of Reference
Section of EA
Socio-economics (local and regional)
Volume K, Section 1.1
Landscape; includes visual aesthetics
Volume I, Section 11.1
Noise
Volume I, Section 5.1
Concerns and opinions of affected populations
Volume H, Section 5
II-3 Project Description
Separate description for mine
Volume B, Section 2
Separate description for slurry pipeline
Volume C, Section 2
Separate description for the process plant
Volume D, Section 2
Separate description for the tailings facility
Volume E, Section 2
Separate description for the port
Volume F, Section 2
Separate description for the limestone quarry
Not now in project; see Volume A, Section 3
3.1 Planning
Volume A, Section 3; Volume B, Section 2;
Volume C, Section 2; Volume D, Section 2
3.2 Construction
Volume A, Section 3; Volume B, Section 2;
Volume C, Section 2; Volume D, Section 2
3.3 Mining
Volume A, Section 3; Volume B, Section 2;
Volume C, Section 2; Volume D, Section 2
3.3.1 Similar cases : one or several other projects to be described
Volume A, Section 4
3.3.2 Cross sectoral studies
Land purchase plan
Sections 2, 5.1 in Volumes B – F
Human development and re-settlement plan
Sections 5.1 in Volumes B – F, Volume G,
Section 4.1
Economic analysis and value added aspects for Madagascar
Sections 5.1 in Volumes B – F, Volume G,
Section 4.1
3.3.3 Dynatec – community partnerships during exploration
Volume A, Section 2
3.4 Closure and post-closure
Mine
Volume B, Section 6
Port
Volume F, Section 6
General restoration of reclaimed areas
Volume H, Section 6
Tailings Facility
Volume E, Section 6
Closure and reclamation of buildings
Volume H, Section 6
Plant
Volume D, Section 6
Slurry Pipeline
Volume C, Section 6
January 2006
Ambatovy Project — A-3
1...,50,51,52,53,54,55,56,57,58,59 61,62,63,64,65,66,67,68,69,70-71,...146